RE: the M3 milestone
FYI, my 2 projects are open and built up on sourceforge now too.
Panic Handler Enhancements - http://panicsel.sourceforge.net 
RAID 1 Support    - http://scsirastools.sourceforge.net 

Any comments are welcome.

Andy

-----Original Message-----
From: Peddibhotla, Rammohan [mailto:rammohan.peddibhotla at intel.com] 
Sent: Friday, September 13, 2002 8:27 PM
To: 'cgl_proof_subgroup at osdl.org'; 'cgl_valid_subgroup at osdl.org'
Cc: 'cgl_tech_board at osdl.org'; 'cgl_discussion at osdl.org';
'johannes.jaskari at nokia.com'
Subject: [cgl_discussion] [CGLE 1.0] Release Coordination Meeting Minutes -
9/12/02

CGLE 1.0 Release Coordination Meeting Minutes- 9/12/02
==========================================


Attendees:
========

Tim Anderson, Khalid Aziz, Ben Cahill, Terence Chen, Randy Dunlap, 
Stephanie Glass, Mark Haverkamp, Sandy Hoag, Dave Howell, 
Venkat Jagana, Johannes Jaskari, Mika Kukkonen,  Ville Lavonious, 
Rusty Lynch, Ram Peddibhotla, Lisa Perry, Tariq Shureih, 
Taneli Vahakangas, Mauri Whalen


Summary of Discussion:
==================

- Milestone M3 Development (due 10/4)

   * Most of the development items are on track for 10/4 check in.

   * The following development tasks have open issues that need to be 
      resolved in the PoC:
        - Hot device identity: Need to finalize scope of the project
        - Watchdog timer: Which implementation to use
        - LTT: Correlation to requirements spec
        - Application loading: How to handle glibc changes 
        - Kernel dumps: Does existing impl meet req 4.2.1

   * Driver hardening project is now open on sourceforge at
     http://hardeneddrivers.sourceforge.net. All participants are invited to

     join the project and contribute to the review of driver hardening draft
spec.

- Milestone M3 Validation Suites (due 10/4)

   * Validation suite development for most of the items is on track. Status
      update on the open items above is on hold pending resolution.

   * Validation subgroup has completed the framework and mechanics of
      submitting test suites. 

   * Validation maintainers are now finalized for all items, except for the
known
      open on IPv6.

- Opens:
   * IPv6 maintainer issue: Further discussion but no resolution yet. This
topic
     to be discussed at Helsinki F2F.

- ARs:
   * All: Subscribe to and participate in driver hardening discussions
   * Mika: What are the consequences of having an integration resource
              as IPv6 maintainer?
   * Mika: Clarify role of maintainer on well established projects as
opposed
               to projects newly created.


Updated milestone plan & AR list
========================
Available at:
http://developer.osdl.org/projects/?action=83952905&project_id=1


Proposed agenda for next week's meeting:
===============================

- 08:30 - 09:00 am      CGLE 1.0 milestone M3 development tracking

- 09:00 - 09:40 am      CGLE 1.0 milestone M3 validation tracking

- 09:40 - 10:00 am      Opens & ARs
_______________________________________________
cgl_discussion mailing list
cgl_discussion at lists.osdl.org
http://lists.osdl.org/mailman/listinfo/cgl_discussion



More information about the cgl_discussion mailing list