[cgl_discussion] POC 6/5 Meeting Minutes

Rusty Lynch rusty at linux.co.intel.com
Fri Jun 6 09:10:24 PDT 2003


On Fri, 2003-06-06 at 08:50, Fleischer, Julie N wrote:
> > > AR Julie to do gap analysis on Security for priority 1 requirements.
> > > AR Rusty to add Gap analysis field to priority 1 
> > requirements document.
> > 
> > If there are appropriate references that come out of the gap analysis,
> > they can be added to the requiremnts document, but I don't think the
> > requirements document is the place for gap analysis information.  This
> > should be tracked in the PoC (perhaps with the PoC list).
> 
> I think this was maybe a typo.  I think it should read that the gap analysis is for the project list that Rusty sent out, not for the requirements document.  I have been putting my gap analysis information in that project list.
> 
> - Julie

Yea, the idea was to capture some high level gap analysis in the
tracking spreadsheet.
    
    --rustyl